MetroCluster Data ONTAP 9.5 Upgrade
Scheduled Maintenance Report for CIT Geneseo Status
Completed
The NetApp MetroCluster Data ONTAP 9.5 upgrade has been completed.
Posted Jun 22, 2020 - 06:48 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 22, 2020 - 05:00 EDT
Scheduled
We will be upgrading our MetroCluster to Data ONTAP version 9.5P12. Nodes in our MetroCluster will be upgraded one at a time, so there should be no interruption of service beyond disconnected sessions from the \\files server momentarily when each node reboots.
Posted Jun 17, 2020 - 14:16 EDT
This scheduled maintenance affected: Campus Services (SAN (Storage Area Network)).